The Kenya Electricity Transmission Company Limited (KETRACO)’s has completed the construction of its substation at Konza Techno City.
The substation, which is part of the Machakos – Konza project will supply electricity to Konza and Machakos environs.
The facility is expected to increase reliability and improve power quality to the areas by providing alternative electricity supply and shortening the length of the existing Athi River – Salama feeder.
The project is financed by the Government of Kenya and EXIM Bank of India at a total cost of USD 13 million.
With a rating of 73MW, the 12km Machakos – Konza transmission line involved the construction of a 132kV single circuit line and two 132/33kV substations at Machakos and Konza. Konza substation will tap a mixture of hydro, geothermal and thermal power through Loop-In-Loop-Out (LILO) arrangement from the existing Juja – Rabai line.
Areas to be fed include Kyumvi, Salama, Athi River and Iposalat from Konza Substation. At Machakos substation, the power will further be fed to Kola, Konza, Katangi, Machakos and two future feeder lines.
Speaking during the energization exercise, KETRACO’s Managing Director & CEO FCPA Fernandes Barasa said that investors from within and outside the country can now invest in Information and Communication Technology (ICT), Health, Tourism and Agriculture sectors among others as they are assured of reliable, efficient and affordable power supply.
“The Konza substation will ensure that Konza Techno City has adequate and reliable power to meet the power needs for the medium term,” said Barasa.
Other projects the Company has implemented include the 220kV Rabai – Malindi – Garsen – Lamu (RMGL) transmission line that will power the Lamu Port South Sudan Ethiopia Transport (LAPSSET) corridor and the Mombasa – Nairobi line that will power the Standard Gauge Railway (SGR) upon its completion later this year.
By 2030, KETRACO will have implemented transmission infrastructure totaling to 16,000km of high voltage transmission lines that are in line with the Vision. The transmission lines, substations and switch gears will facilitate electricity evacuation from generating stations, reinforce the grid network for increased capacity, reliability and provide redundancy.
Financial Fortune is a digital financial news website and print business magazine published in Nairobi by Fortune & Transit Publishers Ltd and covers the financial services sector through news, views and extensive people coverage since 2018. Email: info@financialfortunemedia.com